New Delhi:Detailed Feasibility Report for Pipeline Pandua to Jagdishpur
Disciplines
- Energy Infrastructure
- Oil & Gas
Companies
Dorsch Consult (India) Private Ltd.
Client
GAIL (India) Limited
Duration
From 2003 to 2004Project Activities
- Process Design
- Reconnaissance Survey
- Market Survey
- Identification of Site for stations and tap-off
- Environment Management Plan (EMP)
- Rapid Risk Analysis (RRA)
- System Optimization
- Capital Cost Estimation
- Project Implementation Strategy
- Financial Analysis
Contact
Dorsch Consult (India) Private Ltd.
Mumbai (Headquarters)
401, Shivam Chambers, 4th Floor
S.V. Road, Goregaon (West)
400 062 Mumbai
India
S.V. Road, Goregaon (West)
400 062 Mumbai
India
Phone: +91-22-45 42 81 00
Fax: +91-22-45 42 81 23
E-Mail: dorsch@dcindia.co.in
Description
GAIL is planning to lay a pipeline system under Nationa lGas Grid programme from Haldia to Jagdishpur for transporting 10 MMSCMD of natural gas being outsourced to Pandua, Bangladesh, shall terminate at Jagdishpur in the state of Uttar Pradesh.
The length of proposed pipeline along with throughput would be as follows: from Haldia to Jagdishpur approx. 1100 km, 10 MMSCMD.