Siemensstadt² in Berlin-Spandau:
Energy supply for the new Siemensstadt

Disciplines

  • Energy Infrastructure

Companies

BLS Energieplan GmbH

Client

Siemens

Duration

From 2019 to 2022

Project Activities

Project approach

  • Determination of demand for heating, cooling and electricity for all properties, based on representative 3D models of the buildings
  • Detailed simulation of PV yields
  • Determination of potential for open and probe-based geothermal energy
  • Conception and simulation of supply variants
  • Determination of central ecological parameters

Results

  • Development of a supply concept with minimised CO2 emissions
  • Derivation of regulatory barriers and building blocks to achieve complete CO2 neutrality
  • BLS Energieplan was selected for the further planning of the technical infrastructure.

Contact

BLS Energieplan GmbH

Berlin (Headquarters)
EUREF-Campus 12
D-10829 Berlin
Deutschland

Phone: +49 30 533281-0
E-Mail: info@bls-energieplan.de

View in maps

Description

Occasion and challenges

  • The master plan for Siemensstadt² in Berlin-Spandau is an integrated general plan comprising architecture, urban development, open space and climate planning, rainwater management, energy technology and mobility.
  • The new district is being built on 70 hectares with a gross floor area of one million m².
  • The goal is to create a CO2-free quarter
  • The project combines new construction and listed existing buildings in a highly dense urban space