Berlin:Study on the expansion and upgrading of the media development/infrastructure at the BER site in relation to the Master Plan 2040
Disciplines
- Energy Infrastructure
- Power & Electrical
Companies
BLS Energieplan GmbH
Client
Flughafen Berlin Brandenburg
Duration
From 2020 to 2022Project Activities
- 5-stage project execution with increasing design level
- Comprehensive analysis of the data fragments, completion of the missing planning bases by a self-developed methodology, capacity and demand comparison, presentation of the necessary routes and final project documentation
- Workshop methodology with previously clearly defined work packages (no HOAI)
Contact
BLS Energieplan GmbH
Berlin (Headquarters)
EUREF-Campus 12
D-10829 Berlin
Deutschland
D-10829 Berlin
Deutschland
Phone: +49 30 533281-0
E-Mail: info@bls-energieplan.de
Description
The submitted master plan for 2040 is to be validated with regard to the determined demand values for the energy demand situation including the Capex determination for all 12 quarters. This is a cross-departmental project consisting of consulting, infrastructure, plant engineering and joint venture with Voigt engineers. It represents a strategic project with various stakeholders on the part of FBB (real estate, space marketers, suppliers).
Outcome:
- The 2040 master planning is to be adjusted on an ongoing basis, as it no longer applies to the current situation due to the pandemic
- The stock supply is secured, the nucleus supply can initially be realized by interim measures
- To supply the new buildings and to comply with the climate strategy developed in the project, both SF1 and SF3 must be retrofitted from 2025 onwards
(Partner: Voigt Ingenieure)